Upon the completion of the improvement the executive officer or governing board of the municipality shall file with the appeal board a verified report showing:
1. The location and character of the improvement.
2. The total contract price for the completed improvement.
3. The total actual cost of the completed improvement.
4. By whom, if anyone, the construction was supervised.
5. By whom final inspection was made.
6. Whether or not the improvement complies with its contract, plans, and specifications.
7. Any failure of the contractor to comply with the plans and specifications.
[C24, 27, 31, 35, 39, § 362; C46, 50, 54, 58, 62, 66, 71, 73, 75, 77, 79, 81, § 23.11]
C93, § 73A.11
Referred to in § 390.3
Previous Section 73A.10
Next Section 73A.12
© 2001 Cornell College and League of Women Voters of Iowa
Comments about this site or page?
webmaster@legis.iowa.gov.
Please remember that the person listed above does not vote on bills. Direct all comments concerning legislation to State Legislators.
Last update: Mon Jan 22 17:13:42 CST 2001
URL: /DOCS/IACODE/2001/73A/11.html
jhf