479A.14  Land restoration--standards--inspection.

1.  The board shall adopt rules establishing standards for the restoration of agricultural lands during and after pipeline construction. In addition to the requirements of section 17A.4, the board shall distribute copies of the notice of intended action and opportunity for oral presentations to each county board of supervisors. A county board of supervisors may, under chapter 17A and subsequent to the rulemaking proceedings, petition for additional rulemaking to establish standards for land restoration after pipeline construction within that county. Upon the request of the petitioning county, the board shall schedule a hearing to consider the merits of the petition. Rules adopted under this section shall not apply to land located within city boundaries unless the land is used for agricultural purposes. Rules adopted under this section shall address, but are not limited to, all of the following subject matters:

a.  Topsoil separation and replacement.

b.  Temporary and permanent repair to drain tile.

c.  Removal of rocks and debris from the right-of-way.

d.  Restoration of areas of soil compaction.

e.  Restoration of terraces, waterways, and other erosion control structures.

f.  Revegetation of untilled land.

g.  Future installation of drain tile or soil conservation structures.

h.  Restoration of land slope and contour.

i.  Restoration of areas used for field entrances and temporary roads.

j.  Construction in wet conditions.

k.  Designation of a pipeline company point of contact for landowner inquiries or claims.

2.  The county board of supervisors shall cause an on-site inspection for compliance with the standards adopted under this section to be performed at any pipeline construction project in the county. A licensed professional engineer familiar with the standards adopted under this section and registered under chapter 542B shall be responsible for the inspection. The reasonable costs of the inspection shall be borne by the pipeline company.

3.  If the inspector determines that there has been a violation of the standards adopted under this section, of the land restoration plan, or of an independent agreement on land restoration executed in accordance with subsection 10, the inspector shall give oral notice, followed by written notice, to the pipeline company and the contractor operating for the pipeline company, and order corrective action to be taken in compliance with the standards. The costs of the corrective action shall be borne by the contractor operating for the pipeline company.

4.  An inspector shall adequately inspect underground improvements altered during construction of a pipeline. An inspection shall be conducted at the time of the replacement or repair of the underground improvements. An inspector shall be present on the site at all times at each phase and separate activity of the opening of the trench, the restoration of underground improvements, and backfilling. The pipeline company and its contractor shall keep an inspector continually informed of the work schedule and any schedule changes. If proper notice is given, construction shall not be delayed due to an inspector's failure to be present on the site.

5.  If the pipeline company or its contractor does not comply with the requirements of this section, with the land restoration plan, or with an independent agreement on land restoration executed in accordance with subsection 10, the county board of supervisors may petition the board for an order requiring corrective action to be taken. In addition, the county board of supervisors may file a complaint with the board seeking imposition of civil penalties pursuant to section 479A.16.

6.  The pipeline company shall allow landowners and the inspector to view the proposed center line of the pipeline before commencing trenching operations to ensure that construction takes place in the proper location.

7.  An inspector may temporarily halt the construction if the construction is not in compliance with this chapter and the standards adopted under this chapter, the land restoration plan approved by the board, or the terms of an independent agreement with the pipeline company regarding line location or land restoration executed in accordance with subsection 10, until the inspector consults with the supervisory personnel of the pipeline company.

8.  The board shall instruct inspectors appointed by the county board of supervisors regarding the content of this chapter and the standards and the inspectors' responsibility to require construction conforming with them.

9.  Prior to the initiation of construction, the pipeline company shall file a written land restoration plan with the board describing the methods and procedures by which compliance with this section and the standards adopted under this section will be achieved. The board shall review this plan to insure that the requirements of this section and rules adopted pursuant to this section are met. After board review, the pipeline company shall provide copies of the plan to all landowners of property that will be disturbed by the construction. The requirements of this subsection may be waived by the board to the extent an environmental impact statement addressing the land restoration subjects in subsection 1 was prepared by the federal energy regulatory commission.

10.  This section does not preclude the application of provisions for protecting or restoring property that are different than those prescribed in this section, in rules adopted pursuant to this section, or in the land restoration plan if the alternative provisions are contained in agreements independently executed by the pipeline company and the landowner, and if the alternative provisions are not inconsistent with state law or with rules adopted by the board. Independent agreements on land restoration or line location between the landowner and pipeline company shall be in writing and a copy provided to the county inspector.

11.  For the purposes of this section, "construction" includes the removal of a previously constructed pipeline.

Section History: Recent form

  88 Acts, ch 1074, §14; 95 Acts, ch 192, § 21; 99 Acts, ch 85, §4, 11; 2000 Acts, ch 1080, §1


Previous Section 479A.13

Next Section 479A.15


Return To Home index


© 2001 Cornell College and League of Women Voters of Iowa


Comments about this site or page? webmaster@legis.iowa.gov.
Please remember that the person listed above does not vote on bills. Direct all comments concerning legislation to State Legislators.

Last update: Mon Jan 22 17:13:42 CST 2001
URL: /DOCS/IACODE/2001/479A/14.html
jhf