455B.446  Proceeding.

1.  Within thirty days after the acceptance of the application for a site license, the commission shall establish a timetable for consideration of the application. The timetable for final action by the commission shall not exceed one hundred eighty days after the date the application is accepted.

2.  The proceeding for the issuance of a site license is a contested case under chapter 17A.

3.  The commission shall establish a date for the hearing on the application and shall serve notice of the hearing on interested agencies, as determined by the commission, and regulatory agencies.

The commission shall notify all owners of record of real property located within one mile from the boundaries of the proposed site of the time and place of the hearing.

4.  Notice of the hearing in the form provided in section 17A.12, subsection 2, shall be published in a newspaper of general circulation in each city and county in which the proposed site is located once a week for two consecutive weeks with the second publication being at least twenty days prior to the date of the hearing.

Section History: Early form

  [81 Acts, ch 152, § 6]


Previous Section 455B.445

Next Section 455B.447


Return To Home index


© 2001 Cornell College and League of Women Voters of Iowa


Comments about this site or page? webmaster@legis.iowa.gov.
Please remember that the person listed above does not vote on bills. Direct all comments concerning legislation to State Legislators.

Last update: Mon Jan 22 17:13:42 CST 2001
URL: /DOCS/IACODE/2001/455B/446.html
jhf