357.17  Bond of contractor.

The successful bidder, when awarded a contract, shall be required to give an approved surety bond for one hundred percent of the contract price, guaranteeing completion of the work in accordance with the plans and specifications, and for maintenance, including backfilling, for one year after the final acceptance of the work.

If the contractor shall fail to complete the work as provided in the contract, or shall abandon the same, or fail to proceed in a reasonable manner toward its final completion, the board may proceed against the contractor and surety as provided in sections 468.104 and 468.105.

Section History: Early form

  [C39, § 5526.17; C46, 50, 54, 58, 62, 66, 71, 73, 75, 77, 79, 81, § 357.17]


Previous Section 357.16

Next Section 357.18


Return To Home index


© 1999 Cornell College and League of Women Voters of Iowa


Comments about this site or page? webmaster@legis.iowa.gov.
Please remember that the person listed above does not vote on bills. Direct all comments concerning legislation to State Legislators.

Last update: Thu Mar 18 15:00:31 CST 1999
URL: /DOCS/IACODE/1999/357/17.html
jhf