Notwithstanding any provision to the contrary, a claim by a person furnishing only materials to a subcontractor who is furnishing only materials shall not be entitled to a lien under this chapter unless the person furnishing materials had notified the principal contractor within thirty days of the furnishing of the materials and the lien claim is supported by a certified statement that the principal contractor had been notified within thirty days after the materials were furnished. This requirement is in addition to all other requirements of this chapter.