House Study Bill 259
HOUSE FILE
BY (PROPOSED COMMITTEE ON
ENVIRONMENTAL PROTECTION
BILL BY CHAIRPERSON GREINER)
Passed House, Date Passed Senate, Date
Vote: Ayes Nays Vote: Ayes Nays
Approved
A BILL FOR
1 An Act relating to certification requirements for installers of
2 geothermal heating units.
3 BE IT ENACTED BY THE GENERAL ASSEMBLY OF THE STATE OF IOWA:
4 TLSB 3137HC 81
5 tm/pj/5
PAG LIN
1 1 Section 1. Section 455B.190A, Code 2005, is amended by
1 2 adding the following new subsection:
1 3 NEW SUBSECTION. 8. A geothermal heating unit shall only
1 4 be installed by a certified well contractor that has been
1 5 certified by the department to install such units. The
1 6 department shall certify a person to install geothermal
1 7 heating units after all of the following are satisfied:
1 8 a. The person is certified as a well contractor.
1 9 b. The person has spent at least two years under the
1 10 direct supervision of a certified well contractor.
1 11 EXPLANATION
1 12 This bill provides that a geothermal heating unit shall
1 13 only be installed by a certified well contractor. The bill
1 14 requires the department of natural resources to certify a
1 15 person to install geothermal units if the person is certified
1 16 as a well contractor and the person has spent at least two
1 17 years under the direct supervision of a certified well
1 18 contractor.
1 19 LSB 3137HC 81
1 20 tm:nh/pj/5