Senate Amendment 5191


PAG LIN

     1  1    Amend Senate File 2314 as follows:
     1  2 #1.  By striking everything after the enacting clause
     1  3 and inserting:
     1  4    <Section 1.  Section 476.6, Code Supplement 2009, is
     1  5 amended by adding the following new subsection:
     1  6    NEW SUBSECTION.  22.  a.  It is the intent of the
     1  7 general assembly to require certain rate=regulated
     1  8 public utilities to undertake analyses of and
     1  9 preparations for the possible construction of nuclear
     1 10 generating facilities in this state that would be
     1 11 beneficial in a carbon=constrained environment.
     1 12    b.  A rate=regulated electric utility that was
     1 13 subject to a revenue sharing settlement agreement with
     1 14 regard to its electric base rates as of January 1,
     1 15 2010, shall recover, through a rider and pursuant to
     1 16 a tariff filing made on or before December 31, 2013,
     1 17 the reasonable and prudent costs of its analyses of
     1 18 and preparations for the possible construction of
     1 19 facilities of the type referenced in paragraph "a".
     1 20 Cost recovery shall be accomplished by instituting a
     1 21 revenue increase applied in the same percentage amount
     1 22 to each customer class and not designed to recover,
     1 23 on an annual basis, more than five=tenths percent of
     1 24 the electric utility's calendar year 2009 revenues
     1 25 attributable to billed base rates in this state.  At
     1 26 the conclusion of the cost recovery period, which
     1 27 shall extend no more than thirty=six months in total,
     1 28 the board shall conduct a contested case proceeding
     1 29 pursuant to chapter 17A to evaluate the reasonableness
     1 30 and prudence of the cost recovery.  The utility shall
     1 31 file such information with the board as the board deems
     1 32 appropriate, including the filing of an annual report
     1 33 identifying and explaining expenditures identified in
     1 34 the rider as items for cost recovery, and any other
     1 35 information required by the board.  If the board
     1 36 determines that the utility has imprudently incurred
     1 37 costs, or has incurred costs that are less than the
     1 38 amount recovered, the board shall order the utility to
     1 39 modify the rider to adjust the amount recoverable.
     1 40    c.  Costs that may be recovered through the rider
     1 41 described in paragraph "b" shall be consistent with
     1 42 the United States nuclear regulatory guide, section
     1 43 4.7, general site suitability criteria for nuclear
     1 44 power stations, revision two, April 1998, including
     1 45 costs related to the study and use of sites for nuclear
     1 46 generation.
     1 47    Sec. 2.  Section 476.53, Code 2009, is amended to
     1 48 read as follows:
     1 49    476.53  Electric generating and transmission
     1 50 facilities.
     2  1    1.  It is the intent of the general assembly to
     2  2 attract the development of electric power generating
     2  3 and transmission facilities within the state in
     2  4 sufficient quantity to ensure reliable electric service
     2  5 to Iowa consumers and provide economic benefits to
     2  6 the state. It is also the intent of the general
     2  7 assembly to encourage rate=regulated public utilities
     2  8 to consider altering existing electric generating
     2  9 facilities, where reasonable, to manage carbon emission
     2 10 intensity in order to facilitate the transition to a
     2 11 carbon=constrained environment.
     2 12    2.  a.  The general assembly's intent with regard
     2 13 to the development of electric power generating and
     2 14 transmission facilities, or the significant alteration
     2 15 of an existing generating facility as provided in
     2 16 subsection 1, shall be implemented in a manner that is
     2 17 cost=effective and compatible with the environmental
     2 18 policies of the state, as expressed in Title XI.
     2 19    b.  The general assembly's intent with regard to
     2 20 the reliability of electric service to Iowa consumers,
     2 21 as provided in subsection 1, shall be implemented by
     2 22 considering the diversity of the types of fuel used to
     2 23 generate electricity, the availability and reliability
     2 24 of fuel supplies, and the impact of the volatility of
     2 25 fuel costs.
     2 26    3.  For purposes of this section, unless the context
     2 27 otherwise requires, the terms "cogeneration pilot
     2 28 project facility", "energy sales agreement", "qualified
     2 29 cogeneration pilot project facility", and "utility=owned
     2 30 cogeneration pilot project facility" mean the same as
     2 31 defined in section 15.269.
     2 32    4. 3.  a.  The board shall specify in advance, by
     2 33 order issued after a contested case proceeding, the
     2 34 ratemaking principles that will apply when the costs of
     2 35 the electric power generating facility, or alternate
     2 36 energy production facility,cogeneration pilot project
     2 37 facility, or energy sales agreement are included in
     2 38 regulated electric rates whenever a rate=regulated
     2 39 public utility does any of the following:
     2 40    (1)  Files an application pursuant to section 476A.3
     2 41 to construct in Iowa a baseload electric generating
     2 42 facility with a nameplate generating capacity equal
     2 43 to or greater than three hundred megawatts or a
     2 44 combined=cycle electric power generating facility, or
     2 45 an alternative energy production facility as defined
     2 46 in section 476.42, or to significantly alter an
     2 47 existing generating facility.  For purposes of this
     2 48 subparagraph, a significant alteration of an existing
     2 49 generating facility must, in order to qualify for
     2 50 establishment of ratemaking principles, fall into one
     3  1 of the following categories:
     3  2    (a)  Conversion of a coal fueled facility into a gas
     3  3 fueled facility.
     3  4    (b)  Addition of carbon capture and storage
     3  5 facilities at a coal fueled facility.
     3  6    (c)  Addition of gas fueled capability to a coal
     3  7 fueled facility, in order to convert the facility
     3  8 to one that will rely primarily on gas for future
     3  9 generation.
     3 10    (d)  Addition of a biomass fueled capability to a
     3 11 coal fueled facility.
     3 12    With respect to a significant alteration of an
     3 13 existing generating facility, an original facility
     3 14 shall not be required to be either a baseload or
     3 15 a combined=cycle facility.  Only the incremental
     3 16 investment undertaken by a utility under subparagraph
     3 17 divisions (a), (b), (c), or (d) shall be eligible to
     3 18 apply the ratemaking principles established by the
     3 19 order issued pursuant to paragraph "e".  Facilities
     3 20 for which advanced ratemaking principles are obtained
     3 21 pursuant to this section shall not be subject to a
     3 22 subsequent board review pursuant to section 476.6,
     3 23 subsection 21 to the extent that the investment has
     3 24 been considered by the board under this section.  To
     3 25 the extent an eligible utility has been authorized to
     3 26 make capital investments subject to section 476.6,
     3 27 subsection 21, such investments shall not be eligible
     3 28 for ratemaking principles pursuant to this section.
     3 29    (2)  Leases or owns in Iowa, in whole or in part, a
     3 30 new baseload electric power generating facility with a
     3 31 nameplate generating capacity equal to or greater than
     3 32 three hundred megawatts or a combined=cycle electric
     3 33 power generating facility, or a new alternate energy
     3 34 production facility as defined in section 476.42.
     3 35    (3)  Enters into an agreement for the purchase of
     3 36 the electric power output of a qualified cogeneration
     3 37 pilot project facility or constructs a utility=owned
     3 38 cogeneration pilot project facility pursuant to section
     3 39 15.269.
     3 40    b.  In determining the applicable ratemaking
     3 41 principles, the board shall not be limited to
     3 42 traditional ratemaking principles or traditional
     3 43 cost recovery mechanisms.  Among the principles and
     3 44 mechanisms the board may consider, the board has the
     3 45 authority to approve ratemaking principles proposed
     3 46 by a rate=regulated public utility that provide for
     3 47 reasonable restrictions upon the ability of the public
     3 48 utility to seek a general increase in electric rates
     3 49 under section 476.6 for at least three years after the
     3 50 generating facility begins providing service to Iowa
     4  1 customers.
     4  2    c.  In determining the applicable ratemaking
     4  3 principles, the board shall make the following
     4  4 findings:
     4  5    (1)  The rate=regulated public utility has in effect
     4  6 a board=approved energy efficiency plan as required
     4  7 under section 476.6, subsection 16.
     4  8    (2)  The rate=regulated public utility has
     4  9 demonstrated to the board that the public utility
     4 10 has considered other sources for long=term electric
     4 11 supply and that the facility, or lease, or cogeneration
     4 12 pilot project facility is reasonable when compared
     4 13 to other feasible alternative sources of supply.
     4 14 The rate=regulated public utility may satisfy the
     4 15 requirements of this subparagraph through a competitive
     4 16 bidding process, under rules adopted by the board, that
     4 17 demonstrate the facility, energy sales agreement, or
     4 18 lease is a reasonable alternative to meet its electric
     4 19 supply needs.
     4 20    d.  The applicable ratemaking principles shall
     4 21 be determined in a contested case proceeding, which
     4 22 proceeding may be combined with the proceeding for
     4 23 issuance of a certificate conducted pursuant to chapter
     4 24 476A.
     4 25    e.  The order setting forth the applicable
     4 26 ratemaking principles shall be issued prior to the
     4 27 commencement of construction or lease of the facility,
     4 28 or execution of an energy sales agreement related to
     4 29 the cogeneration pilot project facility.
     4 30    f.  Following issuance of the order, the
     4 31 rate=regulated public utility shall have the option of
     4 32 proceeding according to either of the following:
     4 33    (1)  Withdrawing its application for a certificate
     4 34 pursuant to chapter 476A.
     4 35    (2)  Proceeding with the construction or lease
     4 36 of the facility or implementation of an energy sales
     4 37 agreement related to a cogeneration pilot project
     4 38 facility.
     4 39    g.  Notwithstanding any provision of this chapter
     4 40 to the contrary, the ratemaking principles established
     4 41 by the order issued pursuant to paragraph "e" shall
     4 42 be binding with regard to the specific electric power
     4 43 generating facility or cogeneration pilot project
     4 44 facility in any subsequent rate proceeding.
     4 45    5.  4.  The utilities board and the consumer
     4 46 advocate may employ additional temporary staff, or may
     4 47 contract for professional services with persons who
     4 48 are not state employees, as the board and the consumer
     4 49 advocate deem necessary to perform required functions
     4 50 as provided in this section, including but not limited
     5  1 to review of power purchase contracts, review of
     5  2 emission plans and budgets, and review of ratemaking
     5  3 principles proposed for construction or lease of
     5  4 a new generating facility or a cogeneration pilot
     5  5 project facility.  Beginning July 1, 2002, there is
     5  6 appropriated out of any funds in the state treasury not
     5  7 otherwise appropriated, such sums as may be necessary
     5  8 to enable the board and the consumer advocate to
     5  9 hire additional staff and contract for services under
     5 10 this section.  The costs of the additional staff and
     5 11 services shall be assessed to the utilities pursuant to
     5 12 the procedure in section 476.10 and section 475A.6.
     5 13    6.  a.  A qualified cogeneration pilot project
     5 14 facility may file a petition with the board for a
     5 15 determination of the avoided cost of an electric
     5 16 utility as provided in the federal Public Utility
     5 17 Regulatory Policies Act of 1978 and related federal
     5 18 regulations, if such a determination has not been made
     5 19 within the last twenty=four months or if there is
     5 20 reason to believe the avoided cost has changed.
     5 21    b.  The board shall issue its determination of the
     5 22 electric utility's avoided cost within one hundred
     5 23 twenty days after the petition is filed.
     5 24    c.  The board, for good cause shown, may extend the
     5 25 deadline for issuing the decision for an additional
     5 26 period not to exceed one hundred twenty days.
     5 27    d.  The board shall not issue a decision under this
     5 28 subsection without providing notice and an opportunity
     5 29 for hearing.
     5 30    e.  The utilities board and the consumer advocate
     5 31 may employ additional temporary staff, or may contract
     5 32 for professional services with persons who are not
     5 33 state employees, as the board and the consumer advocate
     5 34 deem necessary to perform required functions as
     5 35 provided in this subsection.  There is appropriated
     5 36 out of any funds in the state treasury not otherwise
     5 37 appropriated, such sums as may be necessary to enable
     5 38 the board and the consumer advocate to hire additional
     5 39 staff and contract for services under this section.
     5 40 The costs of the additional staff and services shall
     5 41 be assessed to the electric utility pursuant to the
     5 42 procedure in sections 476.10 and 475A.6.
     5 43    Sec. 3.  EFFECTIVE UPON ENACTMENT.  This Act, being
     5 44 deemed of immediate importance, takes effect upon
     5 45 enactment.>
     5 46 #2.  Title page, by striking lines 1 and 2 and
     5 47 inserting <An Act requiring certain rate=regulated
     5 48 public utilities to undertake analyses of and
     5 49 preparation for the possible construction of low carbon
     5 50 emitting nuclear generating facilities in this state,
     6  1 permitting all rate=regulated public utilities to make
     6  2 significant alterations to an existing generating
     6  3 facility, and including effective date provisions.>


                                        
          TOM HANCOCK
          SF2314.1831 (4) 83
          rn/sc

                                      -1-