1. “Board” means the board of directors of the notification center.
2. “Damage” means any impact with, destruction, impairment, or penetration of, or removal of support from an underground facility, including
damage to its protective coating, housing, or device.
3. “Emergency” means a condition where there is clear and immediate danger to life or health, or essential services, or a potentially significant
loss of property.
4. a. “Excavation” means an operation in which a structure or earth, rock, or other material in or on the ground is moved, removed, or compressed,
or otherwise displaced by means of any tools, equipment, or explosives and includes but is not limited to grading, trenching,
tiling, digging, ditching, drilling, augering, tunneling, scraping, cable or pipe plowing, driving, and demolition of structures. b. “Excavation” does not include normal farming operations, residential, commercial, or similar gardening, the opening of a grave site in
a cemetery, normal activities involved in land surveying pursuant to chapter 542B, operations in a solid waste disposal site which has planned for underground facilities, the replacement of an existing traffic
sign at its current location and at no more than its current depth, and normal road or highway maintenance which does not
change the original grade of the roadway or the ditch.
5. “Excavator” means a person proposing to engage or engaging in excavation.
6. “Forty-eight-hour period” means a period of forty-eight consecutive hours beginning at 6:00 a.m. the next business day from the day the notification
center receives a notice and excludes Saturdays, Sundays, and legal holidays.
7. “Locator” means a person proposing to engage or engaging in the location and marking of underground facilities under contract with
or employed by an operator.
8. “Normal farming operations” means plowing, cultivation, planting, harvesting, and similar operations routine to most farms, but excludes chisel plowing,
sub-soiling, or ripping more than fifteen inches in depth, drain tile excavating, terracing, digging or driving a post in
a new location other than replacing a post while repairing a fence in its existing location, and similar operations.
9. “Notification center” means the statewide notification center established in section 480.3.
10. “Operator” means a person owning or operating an underground facility including but not limited to public, private, and municipal utilities.
An operator does not include a person who owns or otherwise lawfully occupies real property where an underground facility
is located only for the use and benefit of the owner or occupant on the property.
12. “Underground facility” means an item of personal property owned or leased by the operator which is buried or placed below ground for use in connection
with the storage or conveyance of, or the provision of services supplying water, sewage, electronic, telephonic, or telegraphic
communications, electric energy, hazardous liquids, or petroleum products including natural gas or other substances, and includes
but is not limited to pipes, sewers, conduits, cables, valves, lines, wires, manholes, and attachments to such property but
does not include sanitary sewer laterals, storm sewer laterals, and water service lines providing service to abutting private
properties.
480.4 Required notice — location and marking of underground facilities — exception.
1. a. Except as otherwise provided in this section, prior to any excavation, an excavator shall contact the notification center and provide notice of the planned excavation
occurring after a forty-eight-hour period. The notice shall be valid for twenty-five calendar days beginning on the day the
forty-eight-hour period concludes. If all locating and marking of underground facilities is completed prior to the expiration
of the forty-eight-hour period, the excavator may proceed with excavation upon being notified by the notification center that
the locating and marking of all underground facilities is complete. The notification center shall establish a toll-free telephone
number to allow excavators to provide the notice required pursuant to this subsection. b. A notice provided pursuant to this subsection for a location within a city shall include the following information: (1) A street address or block and lot numbers, or both, of the proposed area of excavation.
(2) The name and address of the excavator.
(3) The excavator’s telephone number.
(4) The type and extent of the proposed excavation.
(5) Whether the discharge of explosives is anticipated.
(6) The date and time when excavation is scheduled to begin.
(7) Approximate location of the excavation on the property.
(8) If known, the name of the housing development and property owner.
c. A notice provided pursuant to this subsection for a location outside a city shall include the following information: (1) The name of the county, township, range, and section.
(2) The name and address of the excavator.
(3) The excavator’s telephone number.
(4) The type and extent of the proposed excavation.
(5) Whether the discharge of explosives is anticipated.
(6) The date and time when excavation is scheduled to begin.
(7) Approximate location of the excavation on the property.
(8) If known, the quarter section, 911 address and global positioning system coordinate, name of property owner, name of housing
development with street address or block and lot numbers, or both.
d. For purposes of the requirements of this section, an excavation commences the first time excavation occurs in an area that was not previously identified by the excavator
in an excavation notice.
e. At the time of giving notice to the notification center pursuant to this subsection, an excavator shall use white paint, white flags, white stakes, or a combination thereof, to mark the proposed area of excavation,
unless one of the following applies: (1) The precise location, direction, size, and length of the proposed excavation area can be clearly and adequately defined and
described during the call to the notification center or during an onsite preconstruction meeting.
(2) Electronic means of white-lining is supported by the notification center and used by the excavator.
(3) Physical premarking can be shown to be impractical.
2. The notification center, upon receiving notice from an excavator, shall immediately transmit the information contained in
the notice to each operator in the area of the proposed excavation and provide the names of all operators in that area to
the excavator. The notification center shall assign an inquiry identification number to each notice and shall maintain a record
of each notice for at least six years from the date the notice is received. The notification center shall not assess an operator
who requests in writing not to receive a notification of its own excavations for any portion of the costs associated with
such excavations.
3. a. (1) An operator who receives notice from the notification center shall mark the horizontal location of the operator’s underground
facility and the excavator shall use due care in excavating in the marked area to avoid damaging the underground facility.
The operator shall complete such locating and marking, and shall notify the notification center that the marking is complete
within the forty-eight-hour period unless otherwise agreed by the operator and the excavator. No later than the expiration
of the forty-eight-hour period, the notification center shall notify the excavator of the underground facility locating and
marking status, or the failure of the operator to notify the center that the locating and marking is complete. The locating
and marking of the underground facilities shall be completed at no cost to the excavator. If, in the opinion of the operator,
the planned excavation requires that the precise location of the underground facilities be determined, the excavator, unless
otherwise agreed upon between the excavator and the operator, shall hand dig test holes or use nondestructive methods to determine
the location of the facilities unless the operator specifies an alternate method. (2) (a) The marking required under this subsection shall be done in a manner that will last for a minimum of five working days on any nonpermanent surface, or a minimum of
ten working days on any permanent surface. If the excavation will continue for any period longer than such periods, the operator
shall remark the location of the underground facility upon the request of the excavator. The request shall be made through
the notification center. (b) A locator shall use for marking a flag that includes the name of the operator and a contact phone number.
(3) Unless otherwise agreed by the operator and excavator in writing, no excavation shall be performed within twenty-five feet
of an underground pipeline operating at one hundred fifty pounds per square inch or greater and that is equal to or greater
than two inches in diameter unless a representative of the operator of the underground pipeline is present at the planned
excavation area. This requirement shall not apply, however, when a representative of the operator fails to be present at the
proposed excavation area at the time work is scheduled to commence or as otherwise agreed by the operator and excavator in
writing. In this event, the excavator shall notify the operator that the representative failed to appear, and excavation operations
can begin, provided the excavator uses due care to avoid damaging the underground facilities.
b. An operator who receives notice from the notification center and who determines that the operator does not have any underground
facility located within the proposed area of excavation shall notify the notification center concerning this determination
within the forty-eight-hour period. No later than the expiration of the forty-eight-hour period, the notification center shall
notify the excavator that the operator does not have any underground facilities within the proposed area of excavation.
c. For purposes of this chapter, the “horizontal location of any underground facility” is defined as including an area eighteen inches on either side of the underground facility.
d. For the purposes of this chapter, notifications provided to the excavator by the operator or by the notification center shall be provided in a consistent
manner to be established by the board.
4. An excavator is responsible for preserving the markings required in subsection 3 at all times during the excavation. If the markings will be destroyed or otherwise altered during the excavation, the excavator
must establish suitable reference points which will enable the excavator to locate the underground facility at all times during
the excavation.
5. The operator shall mark the location of any underground facility to conform with the uniform color code established by the
American public works association’s utility location and coordination council.
6. The only exception to this section shall be when an emergency exists. Under such conditions, excavation operations can begin immediately, provided reasonable
precautions are taken to protect the underground facilities. The excavator shall notify the notification center of the excavation
as soon as practical.
92 Acts, ch 1103, §4; 98 Acts, ch 1049, §2; 2014 Acts, ch 1047, §1 – 6; 2018 Acts, ch 1026, §149; 2024 Acts, ch 1120, §5 – 7
480.5 Damage to underground facility — report to operator.
1. An excavator shall as soon as practical notify the operator when any damage occurs to an underground facility as a result
of an excavation. The notice shall include the type of facility damaged and the extent of the damage. If damage occurs, an
excavator shall refrain from backfilling in the immediate area of the underground facilities until the damage has been investigated
by the operator, unless the operator authorizes otherwise.
2. If the damage results in an emergency, the excavator shall take all reasonable actions to alleviate the emergency including
but not limited to the evacuation of the affected area. The excavator shall leave all equipment situated where the equipment
was at the time the emergency was created and immediately contact the operator and appropriate authorities and necessary emergency
response agencies.