1. a. Except as otherwise provided in this section, prior to any excavation, an excavator shall contact the notification center and provide notice of the planned excavation.
This notice must be given at least forty-eight hours prior to the commencement of the excavation, excluding Saturdays, Sundays,
and legal holidays. Notices received after 5:00 p.m. shall be processed as if received at 8:00 a.m. the next business day.
The notice shall be valid for twenty calendar days from the date the notice was provided to the notification center. If all
locating and marking of underground facilities is completed prior to the expiration of the forty-eight-hour period, the excavator
may proceed with excavation upon being notified by the notification center that the locating and marking of all underground
facilities is complete. The notification center shall establish a toll-free telephone number to allow excavators to provide
the notice required pursuant to this subsection. b. A notice provided pursuant to this subsection for a location within a city shall include the following information: (1) A street address or block and lot numbers, or both, of the proposed area of excavation.
(2) The name and address of the excavator.
(3) The excavator’s telephone number.
(4) The type and extent of the proposed excavation.
(5) Whether the discharge of explosives is anticipated.
(6) The date and time when excavation is scheduled to begin.
(7) Approximate location of the excavation on the property.
(8) If known, the name of the housing development and property owner.
c. A notice provided pursuant to this subsection for a location outside a city shall include the following information: (1) The name of the county, township, range, and section.
(2) The name and address of the excavator.
(3) The excavator’s telephone number.
(4) The type and extent of the proposed excavation.
(5) Whether the discharge of explosives is anticipated.
(6) The date and time when excavation is scheduled to begin.
(7) Approximate location of the excavation on the property.
(8) If known, the quarter section, 911 address and global positioning system coordinate, name of property owner, name of housing
development with street address or block and lot numbers, or both.
d. For purposes of the requirements of this section, an excavation commences the first time excavation occurs in an area that was not previously identified by the excavator
in an excavation notice.
e. At the time of giving notice to the notification center pursuant to this subsection, an excavator shall use white paint, white flags, white stakes, or a combination thereof, to mark the proposed area of excavation,
unless one of the following applies: (1) The precise location, direction, size, and length of the proposed excavation area can be clearly and adequately defined and
described during the call to the notification center or during an onsite preconstruction meeting.
(2) Electronic means of white-lining is supported by the notification center and used by the excavator.
(3) Physical premarking can be shown to be impractical.
3. a. (1) An operator who receives notice from the notification center shall mark the horizontal location of the operator’s underground
facility and the excavator shall use due care in excavating in the marked area to avoid damaging the underground facility.
The operator shall complete such locating and marking, and shall notify the notification center that the marking is complete
within forty-eight hours after receiving the notice, excluding Saturdays, Sundays, and legal holidays, unless otherwise agreed
by the operator and the excavator. No later than the expiration of the forty-eight-hour period, excluding Saturdays, Sundays,
and legal holidays, the notification center shall notify the excavator of the underground facility locating and marking status,
or the failure of the operator to notify the center that the locating and marking is complete. The locating and marking of
the underground facilities shall be completed at no cost to the excavator. If, in the opinion of the operator, the planned
excavation requires that the precise location of the underground facilities be determined, the excavator, unless otherwise
agreed upon between the excavator and the operator, shall hand dig test holes to determine the location of the facilities
unless the operator specifies an alternate method. (2) The marking required under this subsection shall be done in a manner that will last for a minimum of five working days on any nonpermanent surface, or a minimum of
ten working days on any permanent surface. If the excavation will continue for any period longer than such periods, the operator
shall remark the location of the underground facility upon the request of the excavator. The request shall be made through
the notification center.
(3) Unless otherwise agreed by the operator and excavator in writing, no excavation shall be performed within twenty-five feet
of an underground natural gas transmission line as defined in 49 C.F.R. §192.3 unless a representative of the operator of the underground natural gas transmission line is present at the planned excavation
area. This requirement shall not apply, however, when a representative of the operator fails to be present at the proposed
excavation area at the time work is scheduled to commence or as otherwise agreed by the operator and excavator in writing.
In this event, the excavator shall notify the operator that the representative failed to appear, and excavation operations
can begin, provided the excavator uses due care to avoid damaging the underground facilities. b. An operator who receives notice from the notification center and who determines that the operator does not have any underground
facility located within the proposed area of excavation shall notify the notification center concerning this determination
within forty-eight hours after receiving the notice, excluding Saturdays, Sundays, and legal holidays. No later than the expiration
of the forty-eight-hour period, excluding Saturdays, Sundays, and legal holidays, the notification center shall notify the
excavator that the operator does not have any underground facilities within the proposed area of excavation.
c. For purposes of this chapter, the “horizontal location of any underground facility” is defined as including an area eighteen inches on either side of the underground facility.
d. For the purposes of this chapter, notifications provided to the excavator by the operator or by the notification center shall be provided in a consistent
manner to be established by the board.