A pipeline company shall not install a subsequent pipeline upon its existing easement when a damage claim from the installation of its previous pipeline has not been determined by negotiation, arbitration or action of the courts. This section does not apply if the damage claim is under litigation or arbitration.
With the exception of claims for damage to drain tile and future crop deficiency, landowners and tenants must submit in writing their claims for damages caused by installation of the pipeline within one year of final cleanup on the real property.
[81 Acts, ch 159, § 2, 4]
© 1996 Cornell College and League of Women Voters of Iowa
Comments? webmaster@legis.iowa.gov.
Last update: Thu Feb 8 18:14:51 CST 1996
URL: /IACODE/1995/479/42.html